- PP-783Getting issue details... STATUS
- Interface: New server log message
- Visibility: Public
- Change Control: Stable
- Synopsis:
If the server is unable to set a time task for is_hooks_sync_done function, then it will record following log message and the job willberequeued."Unable to set task for is_hooks_sync_done, the job will be requeued"
Example:
07/15/2017 15:39:34;0001;Server@c7-dev;Svr;Server@c7-dev;Resourcetemporarilyunavailable (11) in is_hooks_sync_done, Unable to set task for is_hooks_sync_done, the job will be requeued
07/15/2017 15:43:06;0001;Server@c7-dev;Svr;Server@c7-dev;Cannot allocate memory (12) in is_hooks_sync_done, Unable to set task for is_hooks_sync_done, the job will be requeued
07/15/2017 15:46:34;0001;Server@c7-dev;Svr;Server@c7-dev;Cannot allocate memory (12) in check_and_run_jobs, Unable to set task for is_hooks_sync_done, the job will be requeued